dear friends,

ours is a make to order scenario with strategy 20. that we get a sales order the bom explodes and procurement proposals are created with respect to sales order quantity.

now when this sales order is transferred to APO. for ppds what should be the planning procedure and heuristic which plans for a particular sales order.

pls guide.

thanks

vinay

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi vinay,

Under this scenario, you can use Planning procedure as 4 ie Planning in Planning run and and heuristic as SAP_PP_009 Rescheduling Bottom-up.

Regards

R. Senthil Mareeswaran.