System performance has become slow after adding more than 1000 WBSE

Former Member
0 Kudos

Dear SAP Gurus,

We have created 1300 nos of WBSE under one project definition. Now system performance has become slow. If I am changing any status & trying to save the project, system takes around 20 min to save the project.

Since all WBSE are important & required one; hence we can not delete any of WBSE.

Now can you guide me to increase the system performance w/o deleting the existing WBSE.

Thanks & Regards,

Pradip

Accepted Solutions (0)

Answers (2)

Answers (2)

nitin_patoliya
Active Contributor
0 Kudos

maximum no. of level should not be more than 99 in your WBS hierarchy.

sys. will allow you to create up to 10000 nos of WBS in single project.

please refer this SAP note. 206264 for further clearification.

Regreate user by mistake i have posted same ans. two times

Regards

Nitin

Edited by: Nitin Patoliya on Feb 6, 2009 8:30 AM

nitin_patoliya
Active Contributor
0 Kudos

Hi prdeep, you need to consult to BASIS team for the same. A/c to me 1300 no of WBS is not the problem. Just ensure that maximum no. of level should not be more than 99 in your WBS hierarchy.

sys. will allow you to create up to 10000 nos of WBS in single project.

please refer this SAP note. 206264 for further clearification.

Regards

Nitin