Hi,
Where to assign activity cost and activity type.
Prashant
hi,
you never maintain activity cost anywhere
you only maintain
work center
activity type,
cost center
you are assigning work center activity type & work hrs for perticular activity... ( CJ20N)
& in work center you are mention ing cost center & activity type combination... ( CNR1/2/3)
for this cost center & activtiy type combination you maintain rate for perticular period.... (KP26)
through this cost will get reflected........