Activity cost assignment

0 Kudos

Hi,

Where to assign activity cost and activity type.

Prashant

Accepted Solutions (1)

Accepted Solutions (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

hi,

you never maintain activity cost anywhere

you only maintain

work center

activity type,

cost center

you are assigning work center activity type & work hrs for perticular activity... ( CJ20N)

& in work center you are mention ing cost center & activity type combination... ( CNR1/2/3)

for this cost center & activtiy type combination you maintain rate for perticular period.... (KP26)

through this cost will get reflected........

Venkatesh

0 Kudos

Dear Venkatesh,

thanks for your answer. If we change the activity cost in KP26 whether we have to run the program to update the cost or it will automatically get reflected in report.

Regards,

Prashant

Former Member
0 Kudos

hi,

it will change automatically. but this will effect for the future transaction not for the old transactions

Edited by: AP on Jan 29, 2009 11:28 AM

0 Kudos

it is resolved

thank you

Answers (0)