on 01-22-2009 5:39 AM
Hi,
How and where to set APPROVE and TESTING or TESTED status?
Harsh
Hi,
what is PSEG business process please give me some detail.
and i see TESTED system status in the search help while creating project versions; thats what i want to know how and where tested status comes to project.
Harsh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
System status : APPR (approved ) can be set on WBS by the business process PSEG.
For the System status : Testing . Pl tell where are you able to see the same on which object, I think, this status is not set on any PS object. If you give me short word of sys status Testing than, I can help you.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.