I am facing problem with a CAPEX project created automatically thru Appropriation request and approval.
Requested Budget in Appropriation request INR 100000
Transaction CJ30 :
Allocated Budget u201COverallu201D INR 1000000
Distributable Budget 2009 INR 900000
Shortfall INR 10000
The project requires the full allocation of funds INR 100000 to fulfil the requirements as stated in the Appropriation Request.
I can not use CJ30 to edit the project budget as it comes automatically from IM.
Regards
VK
Thanks all.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The original budget of the project must be assigned with IM32, when you need to make a adition of budget you should use IM30 and if you need to reduce the budget use IM38.
Best Regards...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
93 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.