The Mat.Planning field to enter the material planning value for material components ahead of assigning the material to activity is not been seen in the Assignment Tab of Internal Process Activity.
Could any one tell me where to locate it for activation. I have searched in "Define Field Selection for Networks" and not able to find it.
Regards,
Arun.An
Hi,
The Material Planning Allowance field in the Assignments tab is going to appear only if you have maintained a Mat. Planning cost element in the section for Internally Processed Activities on the Activities tab in your network profile. (Tcode: OPUU)
Please let me know if this helps.
jibat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Done
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, It was helpful and worked out.
Regards,
Arunachalam.An
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.