Hi there,

I would like to know how to change the development package from a change requests.

Anybody knows?

Thanks in advance,

Dany Anderson

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

The package is linked to objects.

Call SE03, 'Change Object Directory Entries of Objects in a Request', enter your CR and on the next screen you can doubleclick the objects to change the package.

I'm not sure if there is a possibilitie to change many objects with one click. You can mark the whole block, but have to confirm the change for every object as far as i know

Never do this with objects from sap!

Former Member
0 Kudos

Ulf,

Its solved my problem, but as you said...we have to change one objetct each time.

But anyway, thanks for your aswer.

Regards,

Dany Anderson

Former Member
0 Kudos

you're welcome, glad it helped

Answers (1)

Answers (1)

Former Member
0 Kudos

in se80 have to choose the object

click on 'Lock Overview" button

the top one is the open request

others are release requests

then double click on first request on that list there you can find the object to be insterted

Regards,