on 01-21-2009 10:23 AM
Hi Experts
If i want to copy a Project Profile , is it required to create a new Budgeting profile or the same profile will be updated in New one?
regards
pallavi
you can copy new project profile via OPSA txn--> select the profile which you wanted to copy --> F6 --> give the different name there.
The same way you can copy the profject profile via txn OPS9.
By not defining Budget profile in the your project profile you will be able to selet the budget profile while creation of project.
Regards
Nitin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use same budget profile for new project profile.
Sudhir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It will get copied... no need to assign agiane
Venkatesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.