Hi

I see that i can choose inspection point user field combination in the inspection plan header.

But what i need is to define different combinations for each operation,

Is this possible?

If not do u have any other suggestions?

Thanks,

Alper,

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member186399
Active Contributor
0 Kudos

Dear Alper,

I just meant in config .SPRO > Quality Management > Quality Planning >Inspection Planning >Define Identifier for Inspection Points

you can make use of all the identification field for your purpose ( Text length 18, text length 10, Number length 10, number length 3 )

operation wise what is needed to enter you make use of it

Only a suggestion

Regards

gajesh

former_member186399
Active Contributor
0 Kudos

Dear Alper,

This is not possible as inspection point is defined in the header of the inspection plan

A suggestion will make use of all the Identification in the cinfiguration of the inspection point and use it as per your requirement for different operation

Regards

gajesh

Former Member
0 Kudos

can you please give details? i'm not sure i understood that way