factory calander

Former Member
0 Kudos

HI,

i'm trying to create enterprise structure -shiping point -& need to give factory calender

Factory calendar IN dosen't exists

PL tel me the steps to create factory calender IN (india specific)

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear SAPSD,

T. Code: SCAL

There will be three options.

Step 1:

Click first public holidays and go in change mode.

Click create and create your holidays there and save.(Generally fixed date will be used in the pop up)

Step 2:

Now click Holiday calendar and go in change mode.

Click create and give holdiay cal id and description.

Click assign public holiday and add your holidays one by one and save

Now holiday cal is created.

Step 3:

Now come out and choose Factory calendar and go in change mode.

Click create and give Factory calendar id and description, and validity period. Give the holiday calendar ID.

If you want to give special rule like any of the specific date/ day is the holiday or work day (which is different from holiday calendar you can define) and save.

Step 4:

You have to assign factory calendar to PLANT

T. Code: SM30

Table/View: V_T001W

Double Click on to Plant and go in to details-page. There you will find Field: Factory Calendar.

Best Regards,

Amit

Note: Reference -

http://help.sap.com/saphelp_nw04s/helpdata/en/f0/e702041d3fdd448629b4ee7c00de09/content.htm

Former Member
0 Kudos

HI,

there is a factory calender IN in (friends) system is it possible to copy it on to my system directly

without having to create from scratch.

Pl suggest

Former Member
0 Kudos

Dear SAPSD,

You need to check for details (explained under Step 1, 2, 3; in my previous post). If they suits to your Plant requirement, Attach it.

Best Regards,

Amit

Former Member
0 Kudos

hi,

Is it possible to download IN calander details from system to excel at the attach it in another system

Pl suggest

Answers (2)

Answers (2)

Lakshmipathi
Active Contributor
0 Kudos

Go to TCode oy05 and maintain Factory Calender. The IMG path for this is SAP Netweaver --> General Settings --> Maintain Calender

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi,

We can create factory calender in SCAL t.code

Regards,

Chandra