PS :- Cost planning values

Former Member
0 Kudos

Sirs

we have ISU system in which cost planning is done against the Estimate No.

For given estimate no A project is cretaed with 3 WBS in R/3 , in which costs are captured against the WBS which can be extracted in Cn41 / cji3

Now We want to compare the Estimate cost against the Actual for which we want to

1) either transfer actual cost to seperate table wherein values from estimate can be passed OR

2) Pass the estimate values to PS table similar to cj40 ( against the WBS )

I need to know the tables for the cost planningto fetch the data

Pl help

Regards

Ashish

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi...

Plz refer this links.....

http://bitacorasapabap.files.wordpress.com/2008/02/tablasdesap.pdf

Regards

Chandra