When analyzing the task list in ChaRM (Solution Manager 7.0), sometimes the following message appears when viewing the log of an import action (e.g. import transport request)
"import of request SOME started"
normally, in stead of "SOME" the request number should be shown, so it appears ChaRM somehow has lost the connection to the transport request.
Can someone provide me more info on this message and perhaps explain how this message / situation can be avoided?
Hi
SOME means more than one transport was imported.
Technically the function module which triggers the import has one import parameter "request". If only one request is imported "request" has the value of this transport, if more than one request is imported request has the value "SOME" and the transport numbers are submitted through a table parameter (or import is a project import).
In my opinion this behaviour is correct. SAP does not log all transports because the number of transports can be high. If you want to know which transports were imported you can e.g. use /TMWFLOW/PROJ
Regards
Andy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
84 | |
10 | |
10 | |
10 | |
7 | |
6 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.