Hi,

In My project scnerio, Once I Entered budget, the availability control has to active. After that, I am releasing the budget.

As per My settings, After budget release(CJ32), system is showing AVAC active for WBS Elemnts.

AVAC is not getting activated after Budget amount entered(CJ30).

Have I missed any settings? How to overcome this issue?

regards

Suresh

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

It seems that budget profile is configured to activate AVAC after budget release. If you want AVAC after entering budget and dont want to wait till release, remove Release tick in budget profile in availability control section. You need to reconstruct availability control for that project after doing this change: CJBN.

Regards

Former Member
0 Kudos

HI,

Please check your setting in Budget profile whether "Release" i having tick. if so Release the Budget then the "AVAC" status will set.

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

check your budget profile

txn OPS9

Activation type should be 1 usage blank