At my current client, we are having 45 company codes assigned to one controlling area.My question is around setting of Project Profile/Settlement Profile. How do I manage project profiles?
Also If I am managing few project profiles allowing cross company code settlement, what are the pros and cons of doing this? What are the bare minimums for this with respect to configuration
Thanks
Shiv
projects are cross company codes but must be wuithin oine controlling area - so you are ok
the settlement will be from an object either WBS or network activity
the settlement will happen in the company code that is assigned to either the WBS or network activity
regards project profile create as less as possible - if the only difference is the company code then use templates for different companies, or make company code mandatory forcing the user to enter on creation - this will limit the number of project profiles
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Virendra.
So if I put different Company codes at different WBS, n do the settlement, will it be fine? In such case what company code shall I put on the top WBS (Proj Defn)? Will it matter ?as I am not going to settle the top WBS but only the lower level WBS.
What is the standard practise in such type of scenario?
Thanks
Sarang