How to get commited cost

nitish_govindwar
Participant
0 Kudos

Dear All,

I am modifying one Y-Report and for that I need cost of

1.Open PO awaiting delivery,

2.Stock in WH (assigned to project)

3.Open service PO

and

4.Cost of new asset to be added in ongoing project.

can you suggest me how to get this values from field tables or any other method.

Regards,

Nits

Accepted Solutions (0)

Answers (3)

Answers (3)

nitish_govindwar
Participant
0 Kudos

Thanks for reply.

Regards,

Nitish

Former Member
0 Kudos

Hi,

COOI is the table where you can get the all commitments.

Pick OBJNR from PROJ and pass on to COOI, you have the results

Rgds

Sudhir Reddy

nitish_govindwar
Participant
0 Kudos

Thanks for reply.

Regards,

Nitish

Former Member
0 Kudos

Hi,

You can get these details from Table RPSCO

nitish_govindwar
Participant
0 Kudos

My requirement is not satisfied with table RPSCO.

Plz suggest by which table I can get value not quantity, for Open PO material or service.

It is available in ME2J report, but I need table fields.

Regards,

Nits

nitin_patoliya
Active Contributor
0 Kudos

Try with table COOI pass objnr

Regards