Hi gurus,
Is there anyone who has tried to use /sapapo/mc90 to release DP to SNP in order category other than Forecast? FA/FC and etc.
I was trying to release a Key figure from DP planning book to SNP Planned Receipts category AG, and some other category. The system showed a warning msg about this is not a forecast category, then when I continued, it through out a COM error.
Any suggestion?
Thanks,
Hai
Hasn't anyone tried hitting the "Release: Extended" button in MC90?
Its the same as tcode /sapapo/lcin which allows you to release time series values to orders...
Ken Snyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi hai,
The following is the SAP standard procedure for releasing of demand plan from Dp to SNP in line with categories to be defined.
The order category.
Categories serve to group orders according to different kinds of stocks, goods receipts, goods issues and order types. Enter a category that represents orders or forecasts such as FA or FB. The system creates demand orders with reference to the category in the liveCache order area (also called Order liveCache). The category is determined during the release to SNP as follows:
1. Has a category been entered in the release profile? If yes, this category is used.
2. If no, has a category been set in the definition of the requirements strategy in Customizing? (You define the productu2019s strategy in the Proposed strategy field on the Demand tab page of the product master record.) If yes, this category is used.
3. If no, the category FA (forecasts) is used
Hope this will helps to resolve your query
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
6 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.