Hi,
I am assigning material to nwa and doing advance procurement by using procurement type PIR. Reservation is getting created after release of activity but the same is not getting displayed in MD04.
The items of the reservation are getting displayed in MB23.
what could be the reason for this?
Regards,
B P Singh
SAP Replied back
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You are creating PIR for consumption by dependent requirements, right ? Please see my suggestion in that angle.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Planned Independent requirements (PI) are normally configured for consumption by 'Dependent' requirements. Hence the PIR would have been replaced by the reservation from 'dependent' requirement. You can test and verify the same in development system.
Regards
Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
have you carried out MRP run?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.