Hi,

I am assigning material to nwa and doing advance procurement by using procurement type PIR. Reservation is getting created after release of activity but the same is not getting displayed in MD04.

The items of the reservation are getting displayed in MB23.

what could be the reason for this?

Regards,

B P Singh

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

SAP Replied back

Former Member
0 Kudos

Hi,

You are creating PIR for consumption by dependent requirements, right ? Please see my suggestion in that angle.

Regards

Murali

Former Member
0 Kudos

Hi,

I am assigning the component directly to NWA and creating PIR for that.It is not through dependent requirement.

Regards,

B P Singh

Edited by: B P Singh on Jan 20, 2009 1:11 PM

Former Member
0 Kudos

Hi,

Planned Independent requirements (PI) are normally configured for consumption by 'Dependent' requirements. Hence the PIR would have been replaced by the reservation from 'dependent' requirement. You can test and verify the same in development system.

Regards

Murali

Former Member
0 Kudos

Hi,

I am creating Plan order for ROH only.The same is getting reflected correctly in MD63.

virendra_pal
Active Contributor
0 Kudos

have you carried out MRP run?

Former Member
0 Kudos

Hi,

After running MRP also nothing is taking place.The planned independent requirement is getting displayed in MD63 correctly.