Hi Gurus,
What all can be integration points of SAP PLM with Project Systems.
Can Engineering Change Management (ECM) and DMS plug somewhere with Project Systems.
Regards,
Sachin
Hello Sachin,
The INtegration point of PLM with PS are as follows.
1.PS with DMS with linkage to Document Info Record
2.PS with IPPE
3.PS with Material Master(you can also explode a BOM on network activity to attach a material to an activity through a reference point)
4.PS linkage to CPRO.
unfortunately you cannot monitor ps changes through ecn.
Hopefully this answers your query
regards
kaushik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sachin
Did you come right with this question? If you have please post it here as I am also looking for the same solution.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.