on 01-18-2009 6:31 AM
Hi,
Is that possible to filter the CNE5 report result based on the period and year ?
Data element name: JAHRPER.
Appreciate helps and suggestions.
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
not sure about your question
if you are on ecc6 try txn CNPAWB this givies period year selection
if not CNE5 cannot be filetered by period/ year
but you may be able to write a report using report painter/writer with GJAHR/ PER as input
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I am not sure if i understand your question
when you run CNE1 you transfer to the project version usually version 132 the data for analysing progress
Progress is always analysed upto current period - so I am unable to understand the concept whiohc you are trying to say
moreover what is the data element JAHRPER - I am unable to relate to that be more specific in your queries
Hi Virendra,
The actual requirement I need to do here is to add a new screen field Period/year with the data element
JAHRPER in the Progress Analysis Initial Scree (CNE5).
Users are allow to enter the period and date for the reporting up to. This should default to current period but allow user to change the data.
But, I do not know how to related the Period/Year field enter in the Progress Analysis Initial screen to the report result which is the next screen (Progress Analysis Overview)
Thanks.