Hi Experts
How can I assign a customer to a "Route schedule" (LIKP, AULWE) so that once I create a delivery for this customer (VL01N), the "route schedule" is brought automatically by the systeme.
Thanks
Hachim
Hi,
As per my understanding Route schedule is assigned to a route and required to be activated at shipping point, sales document type and delivery type level.
I doubt if it can be assigned to a particular customer in standard SAP.
The rout for a customer is determined thru transport zone of that customer and shipping point and shipping condition.
Whatever the schedule you have maintained for that rout will reflect in sales document.
http://help.sap.com/saphelp_46c/helpdata/en/35/b0e83887a62488e10000009b38f9b7/frameset.htm
http://help.sap.com/saphelp_46c/helpdata/en/dd/560e08545a11d1a7020000e829fd11/frameset.htm
Regards,
Abhee.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.