in the rescheduling sort criteria, there is "document item" (to set the priority to).
What does it do? Does it read the Item number?
Another question is: if i want to set up the rescheduling not to prioritise PO over SO, and other way around either, is it enough to set priority "5" to document category? Will it reschedule in paralel if i set up Date of creation as priority 1, delivery priority as 2, and document number as 3? I am afraid, having 2 different number ranges for PO and SO, it will start prioritising one of them because if the number range anyway?
Thanks in advance for advice!!
cheers,
Bea
Hi Beata,
The item is the item number form the sales order. If you want one of the criteria not to be taken into account you can put 0 next to it. If you want to reschedule both STO and SO according to date and time of creation is rather challenging... I'm affraid you have to prioritize either sales order or STO.
Regards,
Marcin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.