Material Consumed in a Project

shareeq_hussain
Active Participant
0 Kudos

Dear Experts,

I would like to know if there is any Standard report to know the Material Consumed in a Project .

Thanks a lot in Advance

Regards,

Shareeq

Edited by: K M AHAMED SHAREEQ HUSSAIN on Jan 15, 2009 12:45 PM

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

U can also use CN52N...here u can add the fields to see the requirement qty and withdrawl quantity

Answers (1)

Answers (1)

Former Member
0 Kudos

Check Transaction MBBS.

Former Member
0 Kudos

hi,

you can check the same in MB26 report by giving the WBS elements. and also in CJI3 Actual cost liine report