Diff b/w the Avaialbility check(Daily reqmnt)& Individual reqrmnt in MMR

Former Member
0 Kudos

Hi All,

What is the difference between the Avaialbility check 01 (Daily requirement) and 02 (Individual Requirement) in material master?

Thanks

Manish.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi manish,

01 and 02 are the checking group.

Availability check is carried out with the help of these checking group and checking rule.

Checking group 01 and 02 are maintained on the material master.

01 - Individual requirement -For this system generates transfers the requirement for each order to the MRP .So that MM can either produce or procure.

02- Collective requirement.-In this all the requirements in a day or in a week are processed at a time. System stores all request and passes on to the MRP in MRP run.

Anil

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Manish

a) Daily Requirements

In the standard system, checking group 01 is set up so that daily requirements are passed on to production. This means that there is only one line visible in the stock/requirements list (as shown above) that contains the cumulated quantity for one day, rather than the individual sales orders. The sales order number does not display on the Order line in the stock requirements list.

b) Individual Requirements

A line for individual requirements is created in the availability overview for each sales and distribution document and schedule line. This line contains the order quantity and the number of the document which created the requirement as well as the item number and the requirements class.

Individual requirements have the advantage that the initiating document can be identified (the initiating document is displayed in the availability overview for each requirement).

thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi Lakshmipati.

Thanks for your clarification.

Manish