Hello.

I need to create a settlement rule for network activity, but I dont see the button "Plan settlement".

I can see this button for wbs element, but not in the network activity.

¿Why?

Thanks for read me!.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Planned Settlement is only possible in case of WBS elements. For the network activities the plan is rolled up to the respective WBS. No need to put the settlement rule for that. This is std. behaviour of the system...you won't be able to see the plan settlement option in activity.

Regards

Answers (2)

Answers (2)

venkatesh_kulkarni1
Active Participant
0 Kudos

Fist you need to define stratergies for sttlement rule generation for network...(

& you need to assign settlement Stratergy to network type...

Mention default settlemnt profile to networks.

then,

go to CJ20N

Select activity - edit - cost - Settlement rule...

system generates setllment rule as per statergy mentioned automatically....

if you want you can change by above mentioned way.....

normally you settle networks against respective WBSE .....

Venkatesh

nitin_patoliya
Active Contributor
0 Kudos

In which txn you are referring 'plan settlement' button... provide some details

Regards

Nitin