on 01-14-2009 2:05 PM
Hi all,
Sorry if it is a simple question, But I am from SD module. What is Tcode to create a single delivery documents for all line items in PO. I have 3 line items with Different materials having diffent quantities and there are different delivery dates and different delivery schedule dates. I need to create single delivery. Could you please tell me how to do it? What is the Tcode?
Thanks
Anil
Hi,
VL10D
VL10F
VL10G
Try with above t-codes
Hrishi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
SAP says that one can create a single delivery document for materials having their quantity and delivery date same
so for your query the solution is not possible
Perhaps you need more del documents.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
I have 3 line items with Different materials having diffent quantities and there are different delivery dates and different delivery schedule dates This your statement
When the delivery dates are different fro the items i dont think that you can combine them into single delivery document with any t code
One of the prerequisite of the single delivery or combined delivery is the delivery due date and confirmed quantities in the schedule lines have to be same
Regards
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Srikanth/Raja,
Thanks for your help. Now I have two questions...
1. If there are two items in PO with same delivery dates but materials and quantities to be delivered is different, so in this case ..I can combine these two lines in one delivery. Is it true?
2. There are two line items in PO and I want one delivery document with only one item item..that means I want to combine both line items in PO and create one line item in the delivery document...To do this what are the rules......? Which transaction we can do this?
Thanks
Anil
Hi Anil
For your 1st question , if the delivery date is same but he material and quantity are different also then both can be delivered . So you can combine those two materials into 1 delivery . what you said is true
For your 2nd question , you said you have two line items in PO , but if you want combine them into 1 delivery document , then first of all as they are two different materials you cant combine , but if you have a 3 PO's for the one material only then you can combine into one delivery by using VL10A
Regards
Srinath
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.