Hi,

Requirement is in Exports scenario:

Material should first be sent to port and then from there material will go to respective country.

How to configure this.

Regards

Gaurav jain

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you need to maintain the route for transportation planning, here you need to configure the transportation legs and connectivity points this way you can do it

regards

srini

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Gaurav

Check these threads where I have already proposed similar suggestions.

[Configuration of Export sales |]

[Export Scenario |]

thanks