Hi ,experts:
When I creat a po ,the system displays"Account 410000 requires an assignment to a CO object (Item 1) ",What's wrong ? What can I deal that?
bestregards
Alex
Edited by: yuanyuan yang on Jan 13, 2009 5:54 AM
Hi
Please check
Implementation Guide (IMG): Supplier Relationship Management ® SRM Server ® Cross-Application Basic Settings ® Account Assignment ® Define G/L Account for Product Category and Account Assignment Category
hope you created a SC perfectly correct and this cost and GL account from sc to po must be transfered.
please check cost center and gl account assignment in the above mentioned spro configuration.
still problem persistes check up with FICO consulant and check the valididty of cost center
regards
Muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,Muthu :
Thanks very much .I solved the problem according Note: 945158.
We can do like this :
1、The G/L account must be entered (exception: DP Direct Procurement Scenario), and at least one CO object (for example, cost center, order) with an active OKB9 FI/CO connection must also be entered. If these entries are missing, the system issues the error message KI 235 (see point 3).
OR
2、In OBA5, you can suppress the message or define it as a warning message. Since only error messages are transferred to SRM BBP_PD 047), the system no longer issues this message in SRM. Do not consult the FI/CO team when implementing the changes
But,I can't find the message in OBA5。Can you find it ?