on 01-12-2009 10:29 AM
Hi All.
I am dealing with third party orders scenario.
The order has been made for 10 KG... the GR has been done for 8 KGS and invoice has been created for 8 KGS.
Now because of this quantity difference between billed amont and orderd amount , this order is coming in open order report.
How to make the status of the order complete so that it wont come in the open order report?
Points are assured
Thanks & Regards
HI,
Maintain the rejection reason in VA02 and save the document, it will be closed and you cannot see the document in Open sales orders in VA05.
In the overview screen of the sales order, keep scrolling to your right, you can see Reason for Rejection.
Regards
Vamsi Javaji.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
You need Short close the sales order individually or if you need to do it collectively gthen you need to get a program developed for short closing the order based on the requirenment
for individual go to VA02, got to reason of rejection TAB and assign a reason of rejection for the line items which are open and save
Anurag
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.