Hello,

When change master is created with release key, changes to material master is not possible.

However changes to BOM are possible. If someone wants to make changes possible for material master with release key then how one can do that?

Thanks in advance,

jagruti

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Apply note :159414

Regards,

Sanjay

Former Member
0 Kudos

Hello,

Thanks , issue is resolved.

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

You can create a change master using t-code CC01 and you can maintain and you can maintain the revision level in the objects. Then using this change master you can change the material master . Then automatically the system will create a new revision level.

Using T code CC11 - Create Revision Level ,we can maintain the revision levels.

One more way of doing this is ,using MM02 T code,after going into Basic 1

view,just below the material field,you can find the creation button for revision level

You can come to CC02 T code enter the change number set the Release key values as 01.

Hope clear to you.

Regards,