Dear Experts,

We have some material rejected through UD and placed in blocked stock and now we want to return the material back to the vendor against that PO and want to get the replacement . How to carryout this process and whether we can get the material gainst the same PO ?

Thanks.

Accepted Solutions (1)

Accepted Solutions (1)

former_member186399
Active Contributor
0 Kudos

Hello

You can do it in 2 ways

1) Using Migo

1) Use T code MIGO

2) Return delivery against the material document ( document number Material moved from quality to block)

3) do the processing

2) Using QM

1)Activate 08 inspection

2) Move the material back to QM using movement type 349 MB1b

3) Lot will created.

4) Give the UD and to to stock posting to Return Delivery

Once return delivery done you can do GR for the same quantity against the PO

Regards

gajesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Please go thru the following link and follow the steps.

http://help.sap.com/saphelp_erp60_sp/helpdata/en/d0/0babd9ea5011d1954a00a0c930e04c/content.htm

revert for further clarification

regards

Venkat.V