cancel
Showing results for 
Search instead for 
Did you mean: 

material purchase for wbs element procedure ?

Former Member
0 Kudos

what is step by step procedure for material purchase for wbs element in no stock and no mrp mode.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

thanks!

i have done it,

after that i have done migo and miro also

what next i have to do?

harsh

Former Member
0 Kudos

hi,

you have to run the Settlement to the Project

in transaction CJ88.

Enter the project Def

Period

Fiscal Year

tick on the

detail list

execute.

Former Member
0 Kudos

Thanks!

I have done the above,

how to assign PO to wbs.

Former Member
0 Kudos

hi

When you create Purchase Order

the Account Assignment "P" You have to select

then you proceed with entering the other fields.

When you complete the header in item it will ask for "WBS element"

virendra_pal
Active Contributor
0 Kudos

Go to MM transaction ME21N and create a PO to order material

Use account assignment category P for projects

Assign the PO to WBS

If using Easy cost planning then you can order via execution services