How to assign Release strategy with new PO type

Former Member
0 Kudos

Hi experts,

I have created new PO type but the same is not mapped with release strategy at the time of raising purchase order.

I have done the following steps :

a ). Creation of new doc type via SPRO > MM > PURCHASING > PO > DEFINE PO TYPE

b). Edit characterstics in release strategy via path SPRO > MM > PURCHASING > PO > RELEASE PROECURE FOR PO > EDIT CHARACTERSTICS > VALUES ( MENTION NEW PO TYPE & DESC. HERE )

Still I am unable to find release strategy tab in purchase order. Please help.

Suggestions / Rewards will be highly appreciated.

Regards,

( Rajneesh Gulati )

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi ,

I dont know how much customisation u have complited ,

But for release strategy

1 Following are the imp charecrticities ct04 you have to define

Order type (Purchasing)

Plant

Total net order value ( with table & field)

2.check or create relese group is assighned to appropriate class cl01 (with above charecricities )

3.define relese code ( in this u define release level --supervisor , manager etc)

4.release indicator (block ,release)

5.define the group with strategy in that specify prerequisites,release status,classification (specify to the document & plant you want to maintain)

6.create po me22. In me29 you can release it( unless u cant process)

Dev

former_member192897
Active Contributor
0 Kudos

Maintain the Release Strategy New Values in Release Strategy- Classification / CL24N also. Then you will get the Release Strategy tab in the Purchasing Document.