Hi,
Determine Actual dates is not active in Project Planning Board although I have released WBS Elements and final confirmation for the activities has been done.
I just want to know whether this is the normal behaviour of SAP or something is missing at my end.
The same is active in cj23.
Regards,
B P Singh
it is active in PPB
click on the button set of dates