Dear PS guys
In my company we have PS and PP modulem, bacisally my client is MTO. Here i m confusing about Net Working or Routing. How can we decided the topica related to PS and which related to PP.
I have a lot of confusion on this.
I closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
I have some idea for this one. If network is one of the order then we need not to go for production order. then it is no need to for routing in PP, then is there any chance to routing in PS. Is there any thing for this.
Thanks & Regards
Raj
'
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Please think it once again. At what level we need to run MRP. If u want to run MRP at Project level or Sales Order level. If u want to run MRP at sales order level then we didnt get the project wise dietails. am i right. If u run MRP at Project/WBS level then Project system is not a stastical.
let me know any one have any sugession
thanks
raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear All,
Please think it once again. At what level we need to run MRP. If u want to run MRP at Project level or Sales Order level. If u want to run MRP at sales order level then we didnt get the project wise dietails. am i right. If u run MRP at Project/WBS level then Project system is not a stastical.
let me know any one have any sugession
thanks
raj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi ,
I want to share few things,
1. if you doont have PP Module.. you can use network as an order and activities as routings.....
2. if you are have PP Module then project become statistical... everything comes through PP order....
in this case - just mention Purchase, production , assembly as activities.... transfer BOM against these activities then genrate requirement through MRP RUN...
in this you are maintaining BOM, Routings,......
I hope this will clarify..... if wrong please do suggest...
Venkatesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Is any soluation for this quarry that is diference between Routing and Networking
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.