Hi Gurus

I'm still quite new to SAP PS & cProjects, I'm trying to run a Settlement Process for my Project.

The tasks I have completed so far are:

CAT2 - Time Capture

CATS_APPR_LITE - Time Sheet Approval

CAT7 - CATS Transfer to controlling

SE38 - (DPR_CATS_CPR_TRANSF) - Transfer Time to cProjects

CJI3 - Verify Actual Posted Costs

CJB1 - Generate Settlement Rules

When I then run CJ8G I get no results.

Am I missing config in this area?

Any guidance will be greatly apprecioated.

Regards

Panduranga

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

try running CAT5 (or CATA) to trnafer costs to PS and then run settlement

In your process steps you have transferred costs to c projects but not to R/3 PS

Answers (2)

Answers (2)

Former Member
0 Kudos

Apologies

Was running with incorrect Settlement Variant

Regards

Panduranga

Former Member
0 Kudos

Anyone able to assist please

Former Member
0 Kudos

hi,

try to use CJ88.

Former Member
0 Kudos

with the appropriate period and fiscal year.

Former Member
0 Kudos

Thanks AP but have tried this already with the same result

Former Member
0 Kudos

hi,

What is the System Status of the project. "Set the Status as "TECO" and try

Former Member
0 Kudos

Hi

We don't use a TECO System Status

When I do check the System Status it is: Released->Transferred->Assigned

nitin_patoliya
Active Contributor
0 Kudos

in CJ88 / CJ8G check txn tickmark and try to run.

Regards

Nitin

Former Member
0 Kudos

Hi Nitin

Detail List & Check Trans. Data both checked, same result.

Thanks Panduranga