Hi,
I need information about HR - PS integration Through CATS.
in our scenario, we dont have Activities... we are having only WBSE.
how it will work... ( whether i need to mention any WBSE team for respective WBSE)
can you tell me exact process flow... for CATS means hours bookin, approving....
thanks
Venkatesh
Hi,
Please refer the link as mentioned below
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/CATS/CATS.pdf
Regards
Tushar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Venkatesh,
In your case, you can use WBSE as a cost collector for time booking.
Simple example will be:
In CAT2, input fields are : Person number, WBSE, Cost centre, Activity type & Hrs.
(You need to maintain rate for Cost center & activity type in KP26.)
try creating a WBSe, Release it.
in CAT2, give above details and save the time.
Release the time in CAT2 (otherwise set Release on save indicator in timesheet profile)
Approve the time (CAPP or CATS_APPR_LITE).
Run CATA- select Transfer time to CO.
check WBSE in CJI3.
you will see the cost get posted to WBSE.
Regards, madhu