CN24N - overall Network scheduling

Former Member
0 Kudos

Hello,

No matter how big a range of Projects, WBS elements, networks etc I put for testing this t-code, I am not getting through. I get error as ''No order corresponds to selection criteria". I tried all things. I tried to put only one project, then one wbs but nothing helped. Please help.

Thanks,

`A

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

CN24N is a new transaction for overall network scheduling.

Make sure you have configured the "Define Levels for Networks" properly like Hemant said.

I did have an issue in selecting when I entered a Proj Definition, but I was successful when I just entered the Network Type.  Try that.

Also, see where the network header is assigned.  This might affect the selection.

Former Member
0 Kudos

Hi,

someone have try to execute the transaction CN24N in back ? or define a job ?

Starting with debug the transaction don't execute the F8.

Someone help me.

TK

Davide

Former Member
0 Kudos

Hi,

T- Code CN24N does not exist, i think it is CN24 and for running the same we have to put the network number(either internal / External) not the WBSE or the project definition.

Thanks & regards,

KK

Former Member
0 Kudos

Hi

You need to complete the config. first. SPRO-Project SystemDates-- Scheduling---Define Levels for Network.

Read the documentation for above config. setting given in the same path.

Regards

Former Member
0 Kudos

anybody?