hi experts,

While Iam attaching a material component to internal activity, only I.Activity costs is displayed on planned/actuals report and no material costs are displayed.Can anybody suggest me how to display material costs.

Accepted Solutions (0)

Answers (3)

Answers (3)

venkatesh_kulkarni1
Active Participant
0 Kudos

in addition to the hemants point , please check, cost relavancy in project .

select material- check cost rel check box....

Venaktesh.

Former Member
0 Kudos

I hope ur Project is "Valuated stock". If it is "Non-valuated" then material cost wont be added.

Former Member
0 Kudos

Hi

1.Check material master MM03, accounting 1 tab... whether price is maintained.

2. Check Costing variant used in the network OPL1. Check the valuation strategy for material price determination.

Regards