on 01-07-2009 6:19 AM
Hi PS GURUS!
CAN anyone tell me How REM.ORDER.PLAN is calculated in the system, Wht is the source of information? as iam viewing S_ALR87013558-Drilldown Report-Budget/actual/commt/rem.plan/assign
So I guess the assigned should be the total of actual, RemOrdPlan and the commitment. Is that correct?
Iam confused with REM.ORDER.PLAN.
The system shows Planned Total in CJ31. Wht is the source of information?
Let me know iam very much confused.
REGARDS,
Ansar
Hi Gurus,
Please advise resolution on the above concern. thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
aivanny
There is a way where the system will not calculatr REM value.
Need to apply note: SAP NOTE applied in REM value 853530 for zero.
This resolves my problem.
How is the residual order plan calculated?
Per sales order the following calculation is carried out:
Planning value of the order for planning purposes - actual value of the sales order - commitment value of the order = xxx.If xxx is > 0, the order contributes with xxx to the residual order plan of the WBS element - otherwise it doesn't.
That is, the total of the xxx values (of the amounts > 0) results in the residual order plan value of the WBS element.
Why can I not find any records for the residual order plan in the database?
The residual order plan is only calculated for the runtime of the report.
The residual order plan records in the report do not contain any value category - Is that an error?
This is no error - residual order plan records never contain a value category.
How is column 'Assigned' being calculated?
Column 'Assigned' is a calculated column. It is the total of columns 'Actual' + 'Commitments' + 'Residual Order Plan'. You can view the column definition in Transaction CJE6 for the form and change ot in Transaction CJE5.
Regards,
ahs
thanks so much, that solved the problem!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
project settlement of actual costs (CJ88) does not actually clear the remaining order.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is an error encountered during TECO of the network with remaining order:
Message no. 06 138
Not possible to determine a consumption account
Diagnosis
The system was not able to determine a consumption account for the
purchase order item with account assignment.
Which account is determined is controlled via Customizing with the
function "automatic posting" (transaction/event key GBB).
Procedure
Check your input.
If necessary, contact your system administrator. The latter will be able
to specify an account.
Create automatic postings
next screen:
Error during deletion of purchase requisition
Message no. C2 087
next screen:
Not possible to determine a consumption account
and then it exits the project builder program
Please help, we need to free up the remaining order for the activities under this network
we have not implemented MRP to run in our current implementation. We only use PS for requisitioning (creation of NWA for PRs). We only do project settlement periodically, should regular project settlement (CJ88) clear the remaining order column?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I already tried reconstructing the budget availability control for the project through CJBN but still remaining order is still present and eats up the budget. How do I zero out this value?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
how do we clear the remaining order plan which is the difference of the PR-PO, or the difference with what was goods confirmed from what was POed? Do we just TECO the NWA in Project builder? Please help
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The system shows Planned Total in CJ31. Wht is the source of information?
The rem plan order is the planned value of the production order, not the planned value of the activities. IS that correct?
In some threads i got this information: This value (remaining order) is coming because some project activities have been already release, which has some plan value, but no actual value has been posted till now. IS THAT CORRECT?
let me know the source of information.
Reagrds,
Ansar
Apportioned planned costs of the order - actual cost of the order + commitments of the order = xxx.
If xxx > 0, this xxx represents the contribution of the order to the remaining order plan value of the WBS element - otherwise the contribution is zero.
Wht does it mean, If xxx < 0 , = 0, Iam unable to understand the condition, please pour some light on it,
Regards,
Ansar
Dear Sir,
I came to know that the values which comes under REMORDERPLAN are coming from Reservations which are created against any materials.
Before creating any PR, we can create reservation ..with Network, Network Activity , or Maintenance order. This values comes in REMORDERPLAN, it can be remove by doing Goods issue.I will let you know, currently iam working with this issue..
Regards,
ANSAR
Yes Sir, i agree with you, REMorderplan=Plan-actual-commit,
Now tell me how the system calculate the plan total in budget.
Before i was involved in reservations, but now i came to know that the system calculate the plan total in REMorderplan. According to sapnote 922177, i attached the program.
Let me know the Plan total calculation.
Your help will be appreciated,
Regards,
ANSAR
Assigned value = WBS Commitment + Actual of WBS + Remaining Order Plan + Activity Commitment
Remaining order = Max of (Plan & Acutal ) of activity.
Rem Order Plan will not appear if we the tick Planning Indicator
at IMG: Project System->Structures->Operative Structures->Network->Settings for Networks->Maintain network types
SSanjay