on 01-07-2009 6:17 AM
Dear Experts,
In my project , we are going to implement Pre Investment Analysis. I have done the settings required for pre-investment analysis calculation in IM, can anyone throw some light on FI/CO settings related to preinvestment analysis calculation in IM.
and can anyone give me the requred data for pre investment calculation.
Error I m getting is :
"Internal rate of return cannot be calculated due to the order of data"
Pls. guide.
Thanks,
Sanju.
Hi sanju,
have u done the following steps?
1- Define interst rate for the specific currency
2- define the value date for NPV and IRR
3- Define evaluation type (in market risk management)
4- Define reference interst rate and asign the proper calculation method
5- Define yield curve type
then check in the variant in IM.
Regards
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.