MTA for project progress

Former Member
0 Kudos

Hi Experts,

I am going to use Mile stone trend analysis to track project progress but not able to get the proper graph as expected.

Rather the milestone is being shown as a point in that graphical area. can anybody tell me the further setting in graphical area like time scaling etc to see the graph properly.

What i did:

1- One mile stone created Putting tick mark in MTA relevant and attached to the WBS.

2- I have also created project version which is MTA relevant.

Still not able to get the crt graph, i think some problem in scaling in graphical area,

can any body tell the standard scaling for time/date.

ashis

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ashis,

please refer to SAP note : 360584 - FAQ: MTA (Milestone Trend Analysis)