Hi All,
I met a very strange problem.
First, I use the budget\actual\commitment\rem plan\assign (s_alr_87013558) to look at one lowest level WBS element A. In this report, this WBS element A has budget $4875000, actual $4892399, commitment $26 and assigned $4892426.
Second, I use the CJ31 to display budget. It said current budget $4875000, Distributable $4875000, but the assigned is $4974925.
In order to find why there is a difference, I used CJI3 to check the actual and it is $4892399. Then I used CJI5 to check the commitment and it is 26. I also use CJI8 to check the budget and it is $4875000. And I used CN41 to check there is no order assigned to this WBS element A.
I cannot tell why there is a difference between the assigned amount in s_alr_87013558 and assigned amount in CJ31. I don't think there should be any difference. Can anyone help me to find where the difference come from?
Thanks,
Ting
Please try the following and check
call the WBS-element / project in transaction CJ31.
Display the budget values. Now in the menu choose "Extras->Availability
Control->Analysis". On the pop up confirm year.
Then You see the project structure with the budget values.
Now enter the following command into the "OK-code" field:
=SUM
....
now check whether you a pop-up that 'the assigned values are inconsistent'.
If it is then there is data inconsistency.
For the repair of this values please start the following transactions:
-CJEN (to rebuild the project database)
after this finished start
-CJBN->this rebuilds the assigned values
then run RKANBU01 report in SE38.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is so helpful. I did the CJ31 and then click "Extras->Availability Control->Analysis". I got the list of the line items for the assigned budget. I added the line item up and got the total 4887869.26. But the Assign budget is 4,974,982. So it seems there is data inconsistency. I will do the repair steps.
Thanks a lot!
Ting
Hi all,
I want some clarification on what you have said :
First I went into CJ31. I got into the path you said : Extras->Availability Control->Analysis
We are planning budget at overall level, hence probably i am not getting the year selection pop up. i went inside the report.
I am stuck at this stage : Now enter the following command into the "OK-code" field: =SUM
I am not getting this : OK-CODE field, i am not getting this field. can you guide me on this point to please help me to find out if there is inconsistency. So mean to say if i do this : it will show me a pop-up that 'the assigned values are inconsistent', if data inconsistent.
178837 note : it only says ... try CJBN. I have tried this but the end result is not satisfactory. There is no change in assained value of CJ31 & SLR_xxxxxxx58 report.
Hi,
Please see the note 178837.
thank you.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I found another thing that might cause the problem. All the transaction currency is Eur and CO currency is US dollars. Is that possible that CJ31 is using different exchange rate from the other standard report CJI3 or s_alr_87013558? If it is possilbe, how can we fix this to make sure they are using the same exchange rate?
Thanks,
Ting
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
1. Please check if there is any planned cost coming through network. i.e. if there are any activity costs planned through activity type and cost center. These planned cost will not reflect in s_alr_87013558.
2. If it is the exchange rate issue then you can set it in the report s_alr_87013558. There is a currency tab. (CtrlShiftF4) provided in the report.
Regards