In the cProjects start page, in Task tab dashboard, can this be used to see all the task assigned to me ?
thanks in advance
muthu
Hi,
additionally, following conditions must be met in order to display data in your respective dashboard (e.g. tasks):
- Firstly, you must create a business partner for your cProjects user in the back end using transaction BP for this.
- Activate the "Use Dashboard" indicator in the customizing of your project type.
- Now create a role in the "Resources" area in a project and assign the business partner of your user to this role.
- Save and release the project. Note that the project for displaying in the dashboard cannot not have the status "Created", "Completed" or "Archived".
This also applies to the display of tasks (and checklist items), they must also be released so that they are displayed in the dashboard.
Especially with regard to your 'Task dashboard' -> View "Tasks": the resource connected to your
user must be:
- entered as the "Person Responsible"/"Responsible Resource" in the task
or:
- entered in/assigned to the task as a resource under the "Roles" tab page.
Hope this helps.
Regards,
Silvia
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello!
Yes, this is available in standard. In tasks menu, under task application view, you'll see all the task you're responsible for or assigned to.
Matthias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.