Dear friends,

I am creating P.O. w.r.t.PM.order. WBS is attached in PM order and budget conrol through WBS element. All required setting done in budget profile @ tolerence limit of PS.still BUDGET Is NOT GET CHcheck when i give referece og PM order or PR.generated through pm order.can you help me to check budget in po.In PM order system check budget but not in PO.

Vikas warke

Accepted Solutions (0)

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

if using ps then budget check should not be from pm module

you need to check OPSV and tick the append and apportion indicator for th ePM order type for order category 30

then check

else you need to go through your budget control config

Former Member
0 Kudos

Dear Virendra,

I am controlling through PS budget $ not through PM. I can have budget check on PO by account assignment K ,I also have budget check by internal order no. But If I give PM order no assigned with wbs check is not taking place. I want to know where is integration for this PS-PM I have done reuired changes in opsv but still problem is not solved.