on 01-06-2009 11:24 AM
Hi Gurus
I'm new to SAP PS & cProjects so am battling to understand this error.
I have created a project through cProjects. All of the resources I have utilized for the project share the same Rate code (X01) which has cost of $260.00 & revenue of $330.00
When I view table DPR_RATES_MAP I find only cost rates of $200.00 & $260.00 Depending on the Org Unit.
I have captured time against the project for one of the resources using CAT2 and have approved this time.
Have then run CATS_APPR_LITE to approve the time.
And then SE38 - DPR_CATS_CPR_TRANSF to transfer the confirmation time to cProjects.
When I now run report CATS_DA the cost rate appears as $240.00, not $260.00 as I'm expecting.
Where could this rate be picked up from.
Many Thanks in advance
Panduranga
Resolved.
It was the Activity Type/Price Plan that was being used.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.