Hi Gurus

I'm new to SAP PS & cProjects so am battling to understand this error.

I have created a project through cProjects. All of the resources I have utilized for the project share the same Rate code (X01) which has cost of $260.00 & revenue of $330.00

When I view table DPR_RATES_MAP I find only cost rates of $200.00 & $260.00 Depending on the Org Unit.

I have captured time against the project for one of the resources using CAT2 and have approved this time.

Have then run CATS_APPR_LITE to approve the time.

And then SE38 - DPR_CATS_CPR_TRANSF to transfer the confirmation time to cProjects.

When I now run report CATS_DA the cost rate appears as $240.00, not $260.00 as I'm expecting.

Where could this rate be picked up from.

Many Thanks in advance

Panduranga

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Resolved.

It was the Activity Type/Price Plan that was being used.