Revoke Billing from WBS.

Former Member
0 Kudos

Hi all,

I am facing a problem looking for your help.

I have a WBS element which is marked as Billing WBS, This WBS was assign to SO and billing plan was exist against it. Project is in release status. Now I want to change it back to act assgn only (need to remove billing flag) from WBS. To achieve same I have removed billing plan from SO as well as remove WBS from SO line id. Revoke "order accepted" status. But still I can not able to change its billing indicator.

I could not able to figure out what is wrong? I will not agree to statement that after project is release we cannot change billing indicator (as this is totally wrong).

Can some one please help me out to let me know what I am missing out?

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

once you have disconnected the sales order

run CJEN for the project