cancel
Showing results for 
Search instead for 
Did you mean: 

Additional Material Showing in CN52N report after MRP MD51

atul_rajmane
Participant
0 Kudos

Dear All,

I am attaching a FG material component to the internal activity and exploding bill of material for same. When I am seeing component overview report in CN52N I am getting material list which is attached to activity in Project.

I am doing MRP run MD51 and generating PR. We donu2019t have PP here so only PRu2019s are generated. I using u201CCreate purchase req. u2013 1 Purchase requisitionsu201D in while running MD51.

After running MD51 when I checked CN52N again * am getting an additional material attached to project which doesnu2019t exist in Project Structure. These Items will have same Project WBS (for which activity is attached and BOM exploded earlier) but No network and activity reference.

This case happening inconsistently. Let me know if possible what could be the possible resone for it.

Thanks and Regards,

Atul R. Rajmane

Accepted Solutions (1)

Accepted Solutions (1)

venkatesh_kulkarni1
Active Participant
0 Kudos

Hi,

in CN52N

You are getiing all the materials after MRP Run

you just look at the Resevation - your FG having reservation against project/ network/ activity

remaining all materials having dependent requirement reservation no. for FG.

Venkatesh

atul_rajmane
Participant
0 Kudos

Dear Venkatesh,

Thanks for youor answer. You are right. Its depedant req genrated for FG items.

My Quary is sloved.

Thanks and Regards,

Atul R. Rajmane

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi after mrp run check in MD04 for that finished material

Mrp will explode bom and create depedent requirments

shashank