Schedle line confirmation date is changing to shorter confirmation date

Former Member
0 Kudos

Hi friends,

The confirmed date in the schedule line is not in line with the planned

delivery time maintained in MMR.

When sales order with free of charge document type is created, the

confirmed schedule line is in line with planned del time for a material

of item category ZPTN-free of charge Purchase to order. After coverting

PR to PO the confirmed schedule line had been changed to earlier date

which is not in line with the planned delivery time in MMR.

Please provide your expert views and suggestions..

With warm regards

Jana

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hello, friend.

please check if your purchase requisition has been configured for processing time. then check if the purchase requisition was converted to purchase order within the processing time specified, if any.

regards.