Confirmation of activity on material GR (MIGO for PO)

Former Member
0 Kudos

Hello Friends,

For non stock items, I am generating material requirement in network with item category "N". Based on my project requirement, I am putting requirement date for the material on "General Data" tab of component overview. I want my activity to be confirmed as and when I am making GR for this material. Please assume that there is single component planned for each of the activity.

Can anybody help me ?

Thanks and best regards

Bharat Parikh

Accepted Solutions (1)

Accepted Solutions (1)

former_member214674
Contributor
0 Kudos

Hi,

As per std SAP activity confirmation is a manual activity.

For this kind of scenario you need to go for development !!

Regards

Abhinay Gautam

Former Member
0 Kudos

Closed

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

set confirmations not required for relevant network type in the control key config

this would mean that you do not need to confirm the activities