Hi!

I successfully updated my SOLMAN to SPS 18. As of this patch some new functions has been installed.

I have some questions regarding this.

1) What is the difference between Quality Gate Management and ChaRM?

2) Is Job Scheduling by Redwood free of charge with SAP Solution Manager 7.0 EHP1?

3) Is this useful to install Wily Introscope 8.0 instead of 7.2?

It will be great to get some answers for my questions!

Thank you very much!

regards

Thom

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For your 2nd query, please find the details below.

2) Is Job Scheduling by Redwood free of charge with SAP Solution Manager 7.0 EHP1?

This function is not available by default. To use this function, you must purchase the Process Scheduling for SAP Solution Manager add-on and explicitly activate the function.

http://help.sap.com/saphelp_sm40/helpdata/en/c3/44390086414b4f81a10773b7a11f80/frameset.htm

Also refer to documents available at http://service.sap.com/rkt-solman for more information.

Navigate to "Solution Manager Extension" on the left pane >

Then on the right pane "Process Scheduling Adapter for SAP Solution Manager"

I hope this will help.

Best Regards,

Pradeep Bishnoi

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Thom,

For query

1

1) What is the difference between Quality Gate Management and ChaRM?

check the following link

https://websmp107.sap-ag.de/~form/sapnet?_FRAME=CONTAINER&_OBJECT=011000358700002009112008E

This pdf explains the QGM are the gates at each phases of the project which can control transport request by the Quality manager or board.

This is available in SP18 or ehancement pack 1 onwards........in Change managment Work Center.

CHARM is automation of transport requests across all the system landscape but it doesnt have anything phase wise which is now available in QGM.

2.2) Is Job Scheduling by Redwood free of charge with SAP Solution Manager 7.0 EHP1?

For this already answer is given above that it is not free you have to buy Process Scheduling Adapter

3) Is this useful to install Wily Introscope 8.0 instead of 7.2?

SAP always recommends to use the latest version so better you go for 8.0.